Weekly Stadium Update

Weekly Stadium Update: May 28, 2021

8ace52d3-dfe4-4934-b035-8265ebdac2e4

We’re really focusing on building out the seating in the upper bowl this week as we continue to bring your Nashville SC stadium to life.

We will have no crews working on-site over the Memorial Day Weekend. We hope everyone has a nice and relaxing holiday, and we will see you on the other side!

ongoingactivities
  • Vertical construction continues with ongoing steel work, concrete pouring, masonry walls and decking.
  • Building staircases and elevator rails.
  • Continued work to build stadia, beams, foundations, framing and retaining walls.
  • Slab on deck work continues. This is important for the overall frame and structure of the stadium.
  • Work to build out the framework of the concourse level on the south end.
  • Rough-in work continues, the stage after the framing of the stadium is in place, and various mechanical, electrical, and plumbing lines are being brought in.
  • A range of shallow underground work continues, including plumbing, storm install and electrical work throughout the site.
  • Daily street sweeping on Benton Ave., Bransford Ave., Rains Ave. and Wedgewood Ave. near the entrances to the site. 

If you want to know what’s happening on site at any time just check out the Live Stadium Construction Camera!

Please feel free to reach out to info@nashvillescstadium.com with any questions you have regarding construction.

8ace52d3-dfe4-4934-b035-8265ebdac2e4
774e301f-b654-47f6-919d-763ea1eac972
sitelogisticsheader
sitelogisticsmap
majortruckingheader
truckingroutesmap
Latest
Latest