Weekly Stadium Update

Weekly Stadium Update: April 30, 2021

Stadium Update Image

We are making great progress as we come out of the ground this week to begin exterior plumbing and duct work around the site!

Please visit the Stadium website to see the latest schedule of early morning concrete pours as they are subject to change. The pours begin around 2 a.m. and wrap up around 7 a.m. to reduce the potential impact on neighborhood traffic.

d76588a9-2adc-4118-9344-2d576a7c6e73
e872bf8d-bf83-4ac2-b5fc-081ad0bb99f6
  • Rough-in work continues, the stage after the framing of the stadium is in place, and various mechanical, electrical, and plumbing lines are being brought in.
  • Vertical construction continues with ongoing steel work, concrete pouring and decking.
  • Continued work to build stadia, beams, foundations and retaining walls.
  • Finishing up concrete masonry walls on the field and concourse level.
  • Installing elevator beam connections.
  • Finishing up camera platform work.
  • Slab on deck work continues. This is important for the overall frame and structure of the stadium.
  • Work to build out the framework of the concourse level on the south end.
  • A range of shallow underground work continues, including plumbing, storm install and electrical work throughout the site.
  • Daily street sweeping on Benton Ave., Bransford Ave., Rains Ave. and Wedgewood Ave. near the entrances to the site. 

If you want to know what’s happening on site at any time just check out the Live Stadium Construction Camera!

Please feel free to reach out to info@nashvillescstadium.com with any questions you have regarding construction.

804b7e0d-93eb-4775-8c24-1f7876919c97
2be406b1-a591-4818-adf6-8fef4d590f51
814c068e-6c04-4ac2-8bb2-7b9f59b46a93
0630e448-2217-49eb-b23c-7f48da019f0e
e1b94609-ab16-415d-8973-b70666ab2c0a
5bd9ccc0-c2c9-4357-8adb-d7d7a551887a
Latest
Latest